ROAD WORK PLAN FOR MONDAY JUNE 20

Armor plans to finish paving Vellano and Terazza Crossing tomorrow. 
They need to assess the areas that were already torn out to determine what work needs to be done to fix any issues caused by the rain. 
They hope to start putting in base on Veneterra on Thursday and begin the concrete installation thereafter. 
Obviously, plans are fluid based on what they see tomorrow and how fast the roads dry out. 
I will keep you posted.