UPDATED PLAN FOR JUNE 14, 2016

Attached is an updated map that shows Armor’s plan for the next day or so. As you can see, they plan to lay asphalt patch over the new pipe on Vellano and asphalt Veneterra (east) and Rivanna. They will also complete the pipe on Veneterra and start the removal of the remainder of the road leading down to the cul-de-sac tomorrow. 

On Wednesday they will remove the remaining portion of north Bella Terra Way and start adding in the sub-base.

As the work gets moving on West Veneterra those homes in that area will start experiencing significant access issues. Armor is replacing that area with concrete which will take longer to install. They will help with parking and providing access temporarily.

We will plan on keeping traffic off of the new asphalt on east Veneterra for 24 hours to see if that aids in the curing process.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s