ROAD REPAIR PLAN FOR WEDNESDAY JUNE 8, 2016

Armor again ran into an overly wet soil base on Veneterra this morning. They let it sit hoping it will dry out by tomorrow. If it has dried out they will begin rocking the new sub-base on Veneterra. 

If it’s not dry, they will have to add the component that helps dry it out. Unfortunately that likely won’t happen till Thursday and that means Veneterra will not get finished until Monday. Sorry!!!!

They will likely start to mill the edges on other parts of the neighborhood if this occurs. That process does not limit access or road use. 

Armor will begin with the installation of the drainage pipe on Vellano in the morning. That should not limit anyone’s access. 

If they are able to move forward with Veneterra, it’s possible they will start laying asphalt on Vellano tomorrow. 

Things are in flux, but work will continue in some capacity.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s